Scope of our work
For a company from an international renewable energy group, we prepared the procurement documentation and the main construction contract for four energy storage installations. The work covered the conditions of financing from the Modernisation Fund (Fundusz Modernizacyjny), a change of contractor during implementation and an analysis of the grid connection agreement.
Result and stage of the case
Contract documentation drafted and implemented for projects with a total investment value of PLN 75.6 million. This is the value of the investment, not the amount of a grant obtained by the firm.