Scope of our work
We represented the shareholders of a construction company in a conflict with a third shareholder accused of competing with and harming the company. The quorum and majority provisions of the articles of association made it difficult to decide on his removal from the management board. In January 2023, we obtained interim relief suspending his share rights. The ruling enabled the remaining shareholders to adopt a resolution and unblock the management of the company.
Result and stage of the case
The court suspended the shareholder’s rights for the duration of the proceedings. The interim relief enabled the change in the management board; it was not a final ruling on the exclusion of the shareholder from the company.