Situation
A packaging manufacturer was settling the construction of a hall worth over PLN 14 million. The institution challenged the description of the contract, the evaluation of bids and access to the documentation, announcing a correction of 25% of eligible costs.
Action
The BBS team submitted explanations and objections based on the procurement documentation, the applicable guidelines, the Public Procurement Law (PZP) and case law.
Result and its scope
The institution withdrew the correction in full while the final payment claim was still being settled. The amount of PLN 3.5 million represents a correction avoided, not damages awarded by a court.
The source does not give a court case number; the case ended before a repayment decision was issued.