Four Digital Poland Operational Programme (POPC) projects, four repayment decisions set aside

A foundation running digital education projects received demands for repayment of the entire funding in four projects. The institution terminated all the agreements after an inspection and ordered repayment again after the appellate authority had previously set the decisions aside.

SCALE / RESULT

PLN 2,246,056.77

4 decisions set aside · 2026

Stage
4 decisions set aside · 2026
Published

01 / STARTING POINT

What was the dispute about?

A foundation running digital education projects received demands for repayment of the entire funding in four projects. The institution terminated all the agreements after an inspection and ordered repayment again after the appellate authority had previously set the decisions aside.

02 / OUR WORK

How did we handle the case?

We prepared four complaints, focusing our arguments on the proportion between the shortcomings identified and the demand for repayment of all the funds. We separated the individual tasks and expenditure, as well as the correction mechanism for failure to achieve the indicators.

03 / RESULT

What did we achieve?

The Voivodeship Administrative Court in Warsaw (WSA) set aside all four decisions: V SA/Wa 2454/25, 2657/25, 2658/25 and 2659/25. Three of the cases were heard jointly on 29 May 2026. The decisions covered a total of PLN 2,246,056.77. The cases are returning to the authority; the description does not prejudge the outcome of the reconsidered proceedings.

← All cases and analyses

Public Funding Disputes

Similar cases

  1. Case 1 of 3

    Public funding

    Injunction before the claim

    Court barred enforcement of a promissory note before the trial began

    An institution called on a guarantor to redeem a promissory note, deriving its demand from a guarantee agreement. We challenged the existence of the claim and applied for interim relief even before filing an action for a declaratory judgment. The Regional Court in Warsaw partly granted the application and prohibited the institution from pursuing payment under that promissory note for the duration of the proceedings.

    Krzysztof Brysiewicz, PhDPartner on the case team

    Enforceable interim relief · 2026 · the existence of the claim remains in dispute

  2. Case 2 of 3

    Public funding

    Personal assets

    Repayment of a grant from the private assets of a former management board member

    When enforcement against a company proves ineffective, the institution shifts the debt to the persons who sat on its management board - under Article 116 of the Tax Ordinance in conjunction with Article 67(1) of the Public Finance Act. We conduct such cases before the Voivodeship Administrative Court in Warsaw. We base the defence on the limitation period under Regulation 2988/95 and on the judgment of the Court of Justice in Adjak (C-277/24), according to which a third party must be able to challenge the existence and limitation of the original debt, even if the decision addressed to the company was final.

    Krzysztof Brysiewicz, PhDPartner on the case team

    Cases pending · 2026

  3. Case 3 of 3

    Public funding

    Cassation appeal upheld

    Supreme Administrative Court set aside an unfavourable judgment on a project assessment

    The Voivodeship Administrative Court dismissed a complaint against a project assessment, which was challenged because of the way the competition documentation had been applied. In the cassation appeal we sought examination of the objections within the limits of the requirements published in the competition. The Supreme Administrative Court upheld the cassation appeal and remitted the case for reconsideration.

    Krzysztof Brysiewicz, PhDPartner on the case team

    Procedural result · 4.11.2026 · I GSK 1251/26 · funding has not been awarded