Energy Transition and State Aid in Energy

Geothermal energy: individual consent before the drilling tender

In a geothermal drilling project, one of the two contractors available in Poland was linked to the investor. The ban on awarding a contract to a linked entity could have reduced the procedure to a single realistic bidder.

SCALE / RESULT

PLN 35 million grant

Consent for construction works · 08.06.2018

Stage
Consent for construction works · 08.06.2018
Published

01 / STARTING POINT

What was the dispute about?

In a geothermal drilling project, one of the two contractors available in Poland was linked to the investor. The ban on awarding a contract to a linked entity could have reduced the procedure to a single realistic bidder.

02 / OUR WORK

How did we handle the case?

Before the procedure was launched, we applied to the managing authority for individual consent. We substantiated the effect that excluding the contractor would have on competition and price. We proposed dividing the contract so that the exception would apply only to the necessary scope.

03 / RESULT

What did we achieve?

On 8 June 2018, the institution gave its consent in respect of the construction works. The consent did not cover supplies of machinery or intangible assets. It was an individual decision for a specific project with PLN 35 million in funding.

← All cases and analyses

Public Funding Disputes

Similar cases

  1. Case 1 of 3

    Public funding

    Injunction before the claim

    Court barred enforcement of a promissory note before the trial began

    An institution called on a guarantor to redeem a promissory note, deriving its demand from a guarantee agreement. We challenged the existence of the claim and applied for interim relief even before filing an action for a declaratory judgment. The Regional Court in Warsaw partly granted the application and prohibited the institution from pursuing payment under that promissory note for the duration of the proceedings.

    Krzysztof Brysiewicz, PhDPartner on the case team

    Enforceable interim relief · 2026 · the existence of the claim remains in dispute

  2. Case 2 of 3

    Public funding

    Personal assets

    Repayment of a grant from the private assets of a former management board member

    When enforcement against a company proves ineffective, the institution shifts the debt to the persons who sat on its management board - under Article 116 of the Tax Ordinance in conjunction with Article 67(1) of the Public Finance Act. We conduct such cases before the Voivodeship Administrative Court in Warsaw. We base the defence on the limitation period under Regulation 2988/95 and on the judgment of the Court of Justice in Adjak (C-277/24), according to which a third party must be able to challenge the existence and limitation of the original debt, even if the decision addressed to the company was final.

    Krzysztof Brysiewicz, PhDPartner on the case team

    Cases pending · 2026

  3. Case 3 of 3

    Public funding

    Cassation appeal upheld

    Supreme Administrative Court set aside an unfavourable judgment on a project assessment

    The Voivodeship Administrative Court dismissed a complaint against a project assessment, which was challenged because of the way the competition documentation had been applied. In the cassation appeal we sought examination of the objections within the limits of the requirements published in the competition. The Supreme Administrative Court upheld the cassation appeal and remitted the case for reconsideration.

    Krzysztof Brysiewicz, PhDPartner on the case team

    Procedural result · 4.11.2026 · I GSK 1251/26 · funding has not been awarded

All cases of this practice