Skip to content

Public funding

Demands for repayment of PLN 217 thousand withdrawn before proceedings were initiated

A biotechnology company received two demands for repayment of funds from a research project. The institution linked minor foreign sales with a breach of project durability.

SCALE / RESULT

PLN 217,014.70

Demands withdrawn · 15.11.2018

Stage
Demands withdrawn · 15.11.2018
Published

01 / STARTING POINT

What was the dispute about?

A biotechnology company received two demands for repayment of funds from a research project. The institution linked minor foreign sales with a breach of project durability.

02 / OUR WORK

How did we handle the case?

We demonstrated that the essential research objectives had been achieved and the laboratory had been equipped. We explained the circumstances of commercialisation and the difference between the result of the sales indicator and the durability of the undertaking.

03 / RESULT

What did we achieve?

In a letter of 15 November 2018, the institution found both earlier demands unfounded. Repayment proceedings were not initiated. The description presents a completed intervention at the stage of correspondence preceding a decision.

← All cases and analyses

Public Funding Disputes

Similar cases

  1. Case 1 of 3

    Public funding

    Injunction before the claim

    Court barred enforcement of a promissory note before the trial began

    An institution called on a guarantor to redeem a promissory note, deriving its demand from a guarantee agreement. We challenged the existence of the claim and applied for interim relief even before filing an action for a declaratory judgment. The Regional Court in Warsaw partly granted the application and prohibited the institution from pursuing payment under that promissory note for the duration of the proceedings.

    Krzysztof Brysiewicz, PhDPartner on the case team

    Enforceable interim relief · 2026 · the existence of the claim remains in dispute

  2. Case 2 of 3

    Public funding

    Personal assets

    Repayment of a grant from the private assets of a former management board member

    When enforcement against a company proves ineffective, the institution shifts the debt to the persons who sat on its management board - under Article 116 of the Tax Ordinance in conjunction with Article 67(1) of the Public Finance Act. We conduct such cases before the Voivodeship Administrative Court in Warsaw. We base the defence on the limitation period under Regulation 2988/95 and on the judgment of the Court of Justice in Adjak (C-277/24), according to which a third party must be able to challenge the existence and limitation of the original debt, even if the decision addressed to the company was final.

    Krzysztof Brysiewicz, PhDPartner on the case team

    Cases pending · 2026

  3. Case 3 of 3

    Public funding

    Cassation appeal upheld

    Supreme Administrative Court set aside an unfavourable judgment on a project assessment

    The Voivodeship Administrative Court dismissed a complaint against a project assessment, which was challenged because of the way the competition documentation had been applied. In the cassation appeal we sought examination of the objections within the limits of the requirements published in the competition. The Supreme Administrative Court upheld the cassation appeal and remitted the case for reconsideration.

    Krzysztof Brysiewicz, PhDPartner on the case team

    Procedural result · 4.11.2026 · I GSK 1251/26 · funding has not been awarded