01 / STARTING POINT
What was the dispute about?
A city in the Podlaskie Voivodeship was accused of setting excessive conditions for participation in tenders in two projects: a passive public-use building and the energy modernisation of a school. We had already supported one of these projects in a protest against the negative assessment of its application in 2019.
02 / OUR WORK
How did we handle the case?
We separated the assessment of the breach of procurement rules from the assessment of its effects on the EU budget. We reconstructed the course of construction on the basis of the minutes of site meetings and acceptance reports, the materials documentation and the participants’ explanations. In the second project, we showed that the required manner of documenting experience did not follow from the tender documentation.
03 / RESULT
What did we achieve?
The authority discontinued the proceedings concerning the education centre by a decision of 2 February 2023. In the school case, the Voivodeship Administrative Court in Białystok (WSA) set aside the repayment decision on 16 December 2022 (I SA/Bk 373/22), and after reconsideration the authority also discontinued the proceedings. In both cases, the repayment proceedings ended in discontinuation. The protest upheld earlier had allowed the centre project to return to assessment and obtain funding.