Analysis of the draft implementation of cybersecurity legislation for a renewable energy industry association.

SCALE / OUTCOME

9 regulatory issues

Legal opinion · 2025–2026

Stage
Legal opinion · 2025–2026
Published

Scope of our work

For a renewable energy industry association, we analysed the draft Polish implementation of NIS2, taking into account renewable energy installations and their technology suppliers. Among other things, we examined the deadlines for fulfilling obligations, sanctions and risks to business continuity.

Result and stage of the case

An opinion covering nine identified issues, prepared for the sector’s position in the consultations. It concerns the draft as assessed during the work.

← Back to cases and transactions

Energy Transition and State Aid in Energy

Similar cases

  1. Case 1 of 3

    Public funding

    2 proceedings discontinued

    From a funding protest to two discontinued repayment proceedings

    A city in the Podlaskie Voivodeship was accused of setting excessive conditions for participation in tenders in two projects: a passive public-use building and the energy modernisation of a school. We had already supported one of these projects in a protest against the negative assessment of its application in 2019.

    Discontinuations after a procurement inspection

  2. Case 2 of 3

    Public funding

    PLN 10.73 million applied for

    SMART Pathway (Ścieżka SMART): assessment based on an unclear criterion sent back to the institution

    An application covering an R&D module and an implementation module was rejected in the first call of the SMART Pathway. The refusal was based, among other things, on the concept of “critical R&D work”, which the competition documentation did not define, and on the objection that the schedule was too general.

    Reassessment · judgment of 29.04.2024

  3. Case 3 of 3

    Public funding

    PLN 217,014.70

    Demands for repayment of PLN 217 thousand withdrawn before proceedings were initiated

    A biotechnology company received two demands for repayment of funds from a research project. The institution linked minor foreign sales with a breach of project durability.

    Demands withdrawn · 15.11.2018